Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power

Kyiv Region Energy Defense Under Threat: Temporary Inquiry Commission Reveals Critical Gap in Budget Advance Utilization

🧠 AI Analysis 2 min read 👁 10

Kyiv region faces major issues protecting energy facilities: out of over UAH 800 million in advances, only 3% has been closed by acts, and none of the 26 projects are completed.

Kyiv Region Energy Defense Under Threat: Temporary Inquiry Commission Reveals Critical Gap in Budget Advance Utilization🧠AI Analysis

Photo: Інтерфакс-Україна: загальні

Key points

  • None of the 26 Kyiv region energy engineering defense facilities are completed
  • Only UAH 23 million or 2.79% of UAH 824 million in advances has been covered by acts
  • Most contracts were concluded without open tenders in Prozorro
  • Experts point to a lack of required executive documentation and laboratory test protocols

Ukraine's energy system continues bracing for severe challenges, yet the implementation of second-level engineering protection projects at Kyiv region substations has encountered massive organizational and financial hurdles. According to the Temporary Inquiry Commission of the Verkhovna Rada of Ukraine, not a single one of the 26 planned facilities has been put into operation yet. Meanwhile, contractors have already received colossal amounts of advance payments, the effectiveness of which is raising serious concerns among industry experts.

Million-Hryvnia Advances Without Closed Acts and Procurement Without Prozorro

As reported by Inquiry Commission Head Lesia Zaburanna following treasury and technical audits, the total estimated cost of the works increased from UAH 1.84 billion to UAH 2.28 billion. Out of the UAH 823.99 million in budget advances paid out, primary acts have covered only UAH 23.02 million, or less than 3%. Furthermore, almost the entire portfolio of orders from the Kyiv Regional State Administration's Department of Regional Development was formed without open bidding through the Prozorro system and distributed among a handful of contractors.

"The analysis results record a critical gap between the volumes of budget advances, documented works, and the actual readiness of facilities for winter loads," Lesia Zaburanna stated.

Expert analysis also revealed a specific overlap: LLC "UBC U.B.C." acted not only as a contractor for several agreements but also as the general designer for all 26 facilities. This creates conflict-of-interest risks and requires thorough investigation into the independence of technical supervision. At the same time, certain companies, such as LLC "EASY GROUP", managed to achieve over 50% construction readiness without receiving any advance payments, proving that proper financial discipline and organizational capacity make efficient work possible without multi-million prepayments.

Are Protective Structures Ready for Loads

Beyond financial issues, specialists highlight technical concerns. A second-level protective structure must function as a single engineering contour comprising reinforced concrete structures, ventilation, and fire suppression systems. Partial completion of construction works, even at 50-80%, does not guarantee equipment protection against potential threats. Additionally, several construction sites lack mandatory executive documentation, such as concrete strength laboratory control protocols.

Source Інтерфакс-Україна: загальні — interfax.com.ua/news/general/1237475.html ↗