Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power

Kyiv Region Energy Protection: Parliamentary Inquiry Reveals Critical Gap Between Massive Advances and Actual Construction

🏢 Бізнес 2 min read 👁 8

A Temporary Inquiry Commission of the Verkhovna Rada found that engineering protection projects for Kyiv region energy facilities received hundreds of millions in advance payments, yet none of the 26 sites are completed.

Kyiv Region Energy Protection: Parliamentary Inquiry Reveals Critical Gap Between Massive Advances and Actual Construction🏢Бізнес

Photo: Інтерфакс-Україна: загальні

Key points

  • None of the 26 energy engineering protection facilities in Kyiv region have been completed
  • Contractor advance payments exceeded UAH 823 million, with only 2.79% officially closed by work acts
  • Most contracts were awarded without open tenders via Prozorro to just three main companies

The reliability of critical infrastructure has once again come into focus following the release of verification results by a Temporary Inquiry Commission (TIC) of the Verkhovna Rada of Ukraine. TIC Head Lesia Zaburanna reported a critical gap between allocated budget funds and the actual progress of construction works on level-two engineering protection structures at substations across the Kyiv region. The total estimated cost of these projects has risen to UAH 2.28 billion, with contractors having already received nearly UAH 823.99 million in advance payments.

Multi-Million Advances Without Closed Work Acts

According to treasury and technical verification results, out of over UAH 823 million in disbursed advances, only UAH 23 million (about 2.79%) has been cleared through primary work acceptance acts. Another UAH 87.45 million was paid separately for documented completed works. Meanwhile, approximately UAH 801 million remains in unliquidated advances, requiring immediate verification regarding the actual use of public funds and the availability of building materials.

The commission drew particular attention to the allocation of contracts, most of which were awarded without open tenders via the Prozorro system. The lion's share of funds was concentrated among just three companies: Consulting-Bud, UBC U.B.C., and BK Kyiv Fasad. Notably, UBC U.B.C. served simultaneously as the general designer for all 26 facilities and as a contractor, creating potential conflict of interest risks that require a separate investigation.

Technical Readiness Issues and Documentation Gaps

An expert analysis led by Oleksandr Illarionov indicated that the customer claims an average construction readiness of 53% to 55% for the sites. However, specialists emphasize that a level-two engineering defense structure functions strictly as an integrated protective contour combining reinforced concrete structures, ventilation, and fire suppression systems. Partial construction does not guarantee equipment safety, and as of November, none of the 26 facilities had been fully commissioned.

Additionally, several construction sites lacked mandatory executive documentation, including inspection reports for concealed work and laboratory records verifying concrete strength. As a positive counterexample, the TIC highlighted Easy Group, which achieved 56% construction readiness at its site without receiving any advance payments, proving that timely execution is achievable with proper contractor capacity and financial discipline.