Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power

Engineering Protection of Energy Facilities in Kyiv Region Reaches 55%: Projects Transferred to Restoration Agency

🏢 Бізнес 1 min read 👁 7

The completion rate for the second level of transformer protection in the Kyiv region has reached 55%. Due to delays and funding issues, the project client is being changed.

Engineering Protection of Energy Facilities in Kyiv Region Reaches 55%: Projects Transferred to Restoration Agency🏢Бізнес

Photo: Інтерфакс-Україна: загальні

Key points

  • Transformer protection readiness in Kyiv region hits 55%
  • Projects are being transferred to the Restoration Agency
  • Contractors received over 900 million hryvnias in advance
  • Delays were driven by funding gaps and security protocols

Construction work on the second level of engineering protection for critical infrastructure in the Kyiv region has reached 55% completion. This was announced by Minister for Restoration, Infrastructure, and Transport Mykola Kalashnyk during a meeting with media representatives.

The region's overall resilience plan covers 165 key facilities, including transformer protection across 26 sub-stations of 110 kV. According to the minister, work pace accelerated significantly in the autumn after the government flagged timeline risks and the ministry took direct coordination. While summer progress hovered below one percent weekly due to air raid stoppages and equipment withdrawals, subsequent weekly growth averaged 1.6 percentage points.

Contractors have received 911.44 million hryvnias in advance payments, representing roughly half of the estimated project budget. To mitigate further delays, authorities replaced complete work halts during alerts with risk-monitoring protocols and initiated compensation up to 5 million hryvnias for destroyed or damaged specialized equipment.

Meanwhile, completion rates vary significantly: only three substations exceed 80% readiness, while seven remain at 25-30%. Consequently, the Kyiv Regional Military Administration initiated the transfer of these assets to the Restoration Agency alongside an audit by the State Audit Service to ensure project completion and grid connectivity.

Source Інтерфакс-Україна: загальні — interfax.com.ua/news/general/1236635.html ↗