Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power Saving a Water-Damaged Smartphone: 4 Mistakes to Avoid EU spent more on Russian energy than on aid to Ukraine, European Commission data shows SpaceX hires Washington lobbyists ahead of potential US Congressional probes Geopolitical summit in China: expert assessment of the meeting between US, Chinese, and Russian leaders Strikes on the Crimean Bridge: Economic Impact on Logistics and Shipping EU to Provide €1 Billion for Military Equipment for Ukraine Technological Superiority and the Crimean Bridge: Expert Analysis Zelenskyy Reaffirms Legitimacy of Strikes on Crimean Bridge Russian strike destroys Fresh Production Group's film studio Energy infrastructure in Rivne region damaged by attack: 50 settlements left without power

Kyiv Region Energy Protection Only 55% Complete: Project Transferred to Restoration Agency

🛒 Ціни та тарифи 2 min read 👁 7

Construction of protective structures at 26 vital power substations in the Kyiv region is lagging behind schedule. Management of the project is being transferred to the Restoration Agency, accompanied by a audit of 910+ million UAH in advances.

Kyiv Region Energy Protection Only 55% Complete: Project Transferred to Restoration Agency🛒Ціни та тарифи

Photo: 24tv.ua

Key points

  • Defense structures at 26 key substations in Kyiv region are only 55% complete.
  • Contractors received 911.44 million UAH in advance payments, currently under state audit.
  • Project management is being transferred to the Agency for Restoration.

The construction of second-level protective structures at 26 priority 110 kV power substations in the Kyiv region is currently only 55% complete. This was announced by Minister for Communities and Territories Development Mykola Kalashnyk, detailing the region's infrastructure resilience plan.

Progress Rates and Advance Payments

According to reported data, construction progress remained unsatisfactorily slow for months. By mid-July, readiness stood at 40.02%, increasing by only 0.6 percentage points per week through early October. Following reviews by the State Special Communications Service and direct ministry oversight, weekly progress was brought up to 1.6 percentage points.

In total, contractors received 911.44 million UAH in advance payments. Of this amount, 621.34 million UAH was disbursed prior to mid-July, with an additional 290.1 million UAH allocated later.

Transfer of Authority and Financial Audit

Due to schedule delays, the Kyiv Regional Military Administration decided to transfer construction management to the Agency for Restoration. The agency is tasked with selecting contractors to finish protecting the transformers and reconnecting them to the grid. Concurrently, the State Audit Service will audit the use of public funds.

Concerns over energy infrastructure protection escalated following criticism from President Volodymyr Zelenskyy regarding multi-day power outages in Brovary and Bila Tserkva, where official reports failed to reflect actual ground conditions.

Source 24tv.ua — 24tv.ua/zahist-pidstantsiy-kiyivshhini-gotoviy-55-vidsotkiv-komentar_n3… ↗